Governance for Railway Investment Projects (GRIP)
Governance for Railway Investment Projects (GRIP) is a management and control process developed by Network Rail for delivering projects on the operational railway. Issue 2 of the GRIP Policy Standard (NR/L1/INI/PM/GRIP/100) was published on 3 March 2012.
GRIP was developed to minimise and mitigate the risks associated with projects to enhance or renew the operational railway and projects in a high street environment. It is based on best practice within industries that undertake major infrastructure projects and practice recommended by the bodies including the Association of Project Management (APM) and the Chartered Institute of Building (CIOB).
GRIP is product rather than process driven and divides projects into eight distinct stages:
- Output definition.
- Feasibility.
- Option selection.
- Single option development.
- Detailed design.
- Construction test and commission.
- Scheme hand back.
- Project close out.
Formal reviews examine the project at critical stages in its lifecycle to provide assurance that it can successfully progress to the next stage.
NB GRIP is being replaced by PACE (Project Acceleration in a Controlled Environment) due to concerns that GRIP its bureaucracy and linear process were too inflexible. PACE introduces a model based on principles rather than rules. Network Rail suggest that PACE; ‘… allows project managers to adapt their approach, make decisions that best meet the needs of their project and overlay stages while maintaining rigour.’
[edit] Related articles on Designing Buildings
Featured articles and news
Art of Building CIOB photographic competition public vote
The last week to vote for a winner until 10 January 2025.
The future of the Grenfell Tower site
Principles, promises, recommendations and a decision expected in February 2025.
20 years of the Chartered Environmentalist
If not now, when?
Journeys in Industrious England
Thomas Baskerville’s expeditions in the 1600s.
Top 25 Building Safety Wiki articles of 2024
Take a look what most people have been reading about.
Life and death at Highgate Cemetery
Balancing burials and tourism.
The 25 most read articles on DB for 2024
Design portion to procurement route and all between.
The act of preservation may sometimes be futile.
Twas the site before Christmas...
A rhyme for the industry and a thankyou to our supporters.
Plumbing and heating systems in schools
New apprentice pay rates coming into effect in the new year
Addressing the impact of recent national minimum wage changes.
EBSSA support for the new industry competence structure
The Engineering and Building Services Skills Authority, in working group 2.
Notes from BSRIA Sustainable Futures briefing
From carbon down to the all important customer: Redefining Retrofit for Net Zero Living.
Principal Designer: A New Opportunity for Architects
ACA launches a Principal Designer Register for architects.